Fred Creek Drainage Improvements—Fast Facts


Phase 1
    Start date: October 2007
    Projected completion date: August 2008
    Where it falls: from Evanston Avenue to a point near the south end of the LRC/GC
Phase 2
    Start date: May 2008
    Projected completion date: 2009 (month not yet determined)
    Where it falls: from south of the LRC/GC to where Fred Creek meets Lewis Avenue near the Mabee Center
What the phases entail
  • widening of the banks of Fred Creek
  • alteration of the course of Fred Creek in some areas
  • replacement of existing riprap with pre-cast blocks along embankments
  • addition of terraced landscaping and new vegetation
  • addition of a 10-foot-wide access road/running path along the north bank
  • replacement of the Evanston Avenue box culvert bridge
  • removal of the two existing pedestrian bridges leading from the GC and Christ's Chapel to the Mabee Center parking lot
  • construction of a new pedestrian bridge to the Mabee Center lot, which will be wide enough for vehicular traffic, if necessary
  • replacement of the traffic bridge leading from the Mabee Center parking lot toward the Avenue of Flags

Â